VERIFICATION CHECKLIST – Example1

Verification Details

Project
Example1
Contractor
GAEAQUATIC LTD
Dive Date
06 Aug 2025
Location
Office, Dimitra
Time In (min)
80
Depth Start (m)
10.0
Depth End (m)
10.0
Time Start
08:01
Dive Type
SSE

Control Measures

Documentation

Risk Assessment

Lock-Out Tag-Out

Communication / Monitoring During Execution

Remarks & Communication

dfvb
dfv

(*) If 'No', then additional control measures shall be defined in "Other/Remarks" and these shall be put in place to reduce the risk to ALARP.

(**) The list of control measures is the minimum standard of GAQ. More stringent demands as required by legislation, the contract or following the risk analysis always have priority!

Declaration: the info provided is accurate and the control measures listed above have been effectively implemented at the time of the verification.

Contractor Signature
GAEAQUATIC LTD
Supervisor Signature